Nanisivik Naval Facility -Targeted Structural Repairs
Project Type
Project Replace
Objective
To repair the corrosion in the jetties at Nanisivik to prevent failure.
Requirements
This project will install new steel plates and tension bands over the existing faces of the three jetty cells at the NNF wharf. The jetty cells are deteriorating due ta higher than expected levels of corrosion caused by microorganisms in the water. This project will provide the repairs needed to extend the life of the jetty cells for approximately 15 years, to allow for continued operations until a larger recapitalization project can be implemented.
Funding Range
$20 million to $49 million
Anticipated Timeline (Fiscal Year)
- Options Analysis Phase
- Completed
- Definition Phase
- Completed
- Implementation Phase
- In Progress
- Initial Delivery
- 2025/2026
- Final Delivery
- 2025/2026
Defence Capability Areas
Defence Capability Investment Areas
Key Industrial Capabilities
Not applicable.
Contact Us
Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.
Page details
- Date modified: