Main Facility (AFEC) Bagotville
Project Type
Project New
Objective
To construct a new purpose built facility to accommodate the admin and operation requirements for 2 Wing the RCAF's Air Expeditionary Support Unit.
Requirements
Construct a new 12,852m² facility with spaces for offices, an operation centre, workshops, equipment storage and classrooms. Also develop an exterior storage and parking area of 23, 794m².
Funding Range
$100 million to $249 million
Anticipated Timeline (Fiscal Year)
- Options Analysis Phase
- Completed
- Definition Phase
- Completed
- Implementation Phase
- In Progress
- Initial Delivery
- 2026/2027
- Final Delivery
- 2027/2028
Defence Capability Areas
Defence Capability Investment Areas
Key Industrial Capabilities
Not applicable.
Contact Us
Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.
Page details
- Date modified: