Accommodate 436 Transport Squadron - 8 Wing Trenton
Project Type
Project New/Replace
Objective
The acquisition and delivery of new CC-130J-30 Hercules aircraft has created a need for modernized maintenance facilities. 436 Transport Squadron requires a facility to enable its role in supporting the CAF mandate of force mobility.
Requirements
Project will provide a 4 bay 1st line maintenance hangar for CC130 sized aircraft c/w required storage, shops and workspaces for the entire 436 Transport Squadron personnel along with storage and work space for the Original Equipment Manufacturer.
Funding Range
$250 million to $499 million
Anticipated Timeline (Fiscal Year)
- Options Analysis Phase
- In Progress
- Start Definition
- 2026/2027
- Start Implementation
- 2031/2032
- Initial Delivery
- 2028/2029
- Final Delivery
- 2032/2033
Defence Capability Areas
Defence Capability Investment Areas
Key Industrial Capabilities
Not applicable.
Contact Us
Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.
Page details
- Date modified: