Project | Funding Ranges | Definition Approval | Implementation Approval | Initial Delivery | Final Delivery | Project Sponsor |
---|---|---|---|---|---|---|
Advanced Short Range Missile | $250 million to $499 million | 2023/2024 | 2023/2024 | 2027/2028 | 2029/2030 | Royal Canadian Air Force |
Air Defence System UOR | $250 million to $499 million | 2022/2023 | 2023/2024 | 2024/2025 | 2025/2026 | Canadian Army |
Air Force Omnibus Support Vehicles Replacement (with 6 sub-projects, some of which have been completed and closed) | $50 million to $99 million | In Progress | Partially Completed | Partially Completed | 2025/2026 | Royal Canadian Air Force |
Anti-Tank Guided Missile Replacement | $500 million to $1 billion | 2024/2025 | 2027/2028 | 2028/2029 | 2031/2032 | Canadian Army |
Arctic and Offshore Patrol Ship | $1 billion to $4.99 billion | Completed | In Progress | Completed | 2025/2026 | Royal Canadian Navy |
Armoured Combat Support Vehicle (ACSV) | $1 billion to $4.99 billion | Completed | In Progress | 2023/2024 | 2026/2027 | Canadian Army |
Canadian Surface Combatant | Greater than $5 billion | In Progress | 2024/2025 | 2031/2032 | 2049/2050 | Royal Canadian Navy |
Future Fighter Capability Project | Greater than $5 billion | Completed | In Progress | 2026 | 2032/2034 | Royal Canadian Air Force |
Ground Based Air Defence | $500 million to $1 billion | In Progress | 2024/2025 | 2026/2027 | 2030/2031 | Canadian Army |
Joint Support Ship | $1 billion to $4.99 billion | Completed | In Progress | 2025/2026 | 2027/2028 | Royal Canadian Navy |
LAV Specialist Variant Enhancements (LAV SVE) | $100 million to $249 million | In Progress | 2024/2028 | 2026/2027 | 2027/2028 | Canadian Army |
Lightweight Torpedo Upgrade | $500 million to $1 billion | Completed | In Progress | 2024/2025 | 2029/2030 | Royal Canadian Navy |
Long Range Air-to-Air Missile | $1 billion to $4.99 billion | To be determined | To be determined | To be determined | To be determined | Royal Canadian Air Force |
Medium Range Air-to-Air Missile | $500 million to $1 billion | 2023/2024 | 2023/2024 | 2027/2028 | 2031/2032 | Royal Canadian Air Force |
Portable Anti-X Missile UOR | $50 million to $99 million | In Progress | 2023/2024 | 2024/2025 | 2025/2026 | Canadian Army |
Remotely Piloted Aircraft System (RPAS) Project | $1 billion to $4.99 billion | In Progress | 2023/2024 | 2025/2027 | 2028/2030 | Royal Canadian Air Force |
Victoria-class Modernization (VCM) | $500 million to $1 billion | Completed | In Progress | 2025/2026 | 2032/2033 | Royal Canadian Navy |