GBY- 5 Wing Secondary Runway 16/34 Recap
Project Type
Project Replace
Objective
This project will rebuild the runway to address 5 Wing Goose Bay's secondary crosswind runway infrastructure deficiencies. The secondary crosswind runway is over twice its lifespan since the last pavement rehabilitation, which was completed in 1990.
Requirements
The scope of work will consists of:
- Removing 100mm of asphalt;
- Repairing underlying cracks to full depth;
- Repaving with 100mm of new asphalt;
- Repainting runway lines; and
- Three concrete encased duct banks will be installed for future electrical / lighting and communications system replacement.
Funding Range
$20 million to $49 million
Anticipated Timeline (Fiscal Year)
- Options Analysis Phase
- Completed
- Definition Phase
- Completed
- Implementation Phase
- In Progress
- Initial Delivery
- 2025/2026
- Final Delivery
- 2025/2026
Defence Capability Areas
Defence Capability Investment Areas
Key Industrial Capabilities
Not applicable.
Contact Us
Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.