Joint Task Force 2 Infrastructure

Project Type

Project Replace

Objective

Project includes procurement of land and the construction of purpose-built facility.

Requirements

The project will include procurement of land and the construction of a 99,000 sqm purpose-built facilities for the unit. Will also Include all municipal infrastructure upgrades.

Funding Range

$1 billion to $4.99 billion

Anticipated Timeline (Fiscal Year)

Options Analysis Phase
Completed
Definition Phase
Completed
Implementation Phase
In Progress
Initial Delivery
2033/2034
Final Delivery
2033/2034

Defence Capability Areas

Defence Capability Investment Areas

Key Industrial Capabilities

Not applicable.

Contact Us

Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.

Page details

Date modified: