21 Electronic Warfare Regiment - CFB Kingston
Project Type
Project Replace
Objective
To provide adequate facility to the 2 Electronic Warfare Squadron.
Requirements
Provision of adequate Squadron facility by constructing a new 9,000 m² facility. This will provide office, storage, maintenance, vehicles and training space to house 2 Electronic Warfare Regiment.
Funding Range
$20 million to $49 million
Anticipated Timeline (Fiscal Year)
- Options Analysis Phase
- Completed
- Definition Phase
- Completed
- Implementation Phase
- In Progress
- Initial Delivery
- 2025/2026
- Final Delivery
- 2025/2026
Defence Capability Areas
Defence Capability Investment Areas
Key Industrial Capabilities
Not applicable.
Contact Us
Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.