Language selection

Search


Construct Ammunition Shop - DRDC Valcartier

Project Type

Project Replace

Objective

Construct an ammunition storage shop.

Requirements

To construct an ammunition storage shop of 828 m² and to demolish building #199.

Funding Range

Under $20 million

Anticipated Timeline (Fiscal Year)

Options Analysis Phase
Completed
Definition Phase
Completed
Implementation Phase
In Progress
Initial Delivery
2026/2027
Final Delivery
2026/2027

Defence Capability Areas

Defence Capability Investment Areas

Key Industrial Capabilities

Not applicable.

Contact Us

Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.

Page details

Date modified: