Interim Fighter Capability Project
Project Type
Project New
Objective
The objective of the Interim Fighter Capability Project (IFCP) is to acquire 18 surplus Australian F/A-18A/B aircraft, spares and equipment to supplement Canada’s existing CF-18 fleet to address the fighter capability gap. A secondary objective includes relocation of the Aerospace Engineering Test Establishment from Cold Lake to the Ottawa Airport, including hangar renovations in Ottawa and the relocation of current occupants.
Requirements
Procure 18 operational F/A-18A/B aircraft and spares from Australia and conduct necessary inspections and modifications to introduce these aircraft into operational service with the RCAF. Additionally project will be funding relocation of AETE to increase infrastructure flexibility at 4 Wing.
Funding Range
$250 million to $499 million
Anticipated Timeline (Fiscal Year)
- Options Analysis Phase
- Completed
- Definition Phase
- Completed
- Implementation Phase
- In Progress
- Initial Delivery
- Not applicable
- Final Delivery
- 2026/2027
Defence Capability Areas
Defence Capability Investment Areas
Key Industrial Capabilities
Not applicable.
Contact Us
Do you have any questions or comments about the Defence Capabilities Blueprint? The DCB is managed by the Directorate of Capability Integration at National Defence. To help us connect you with the appropriate subject matter or technical expert, please select whether your query is related to the DCB in general, is related to a project, or if you require technical support. If you request follow up, we will endeavour to acknowledge your request within 7 working days.
Page details
- Date modified: