Project | Funding Ranges | Definition Approval | Implementation Approval | Initial Delivery | Final Delivery | Project Sponsor |
---|---|---|---|---|---|---|
Camp Sustain | $250 million to $499 million | 2025/2026 | 2027/2028 | 2029/2030 | 2031/2032 | Canadian Army |
Tactical Power System | $100 million to $249 million | 2024/2025 | 2026/2027 | 2028/2029 | 2030/2031 | Canadian Army |
Tactical Power System Sustainment Contract | $20 million to $49 million | Not applicable | Not applicable | 2027/2028 | 2049/2050 | Assistant Deputy Minister (Materiel) |